Precast external panels, Harbour Residences
Supply and delivery of architectural precast panels with off-white finish to AS 3600. Drawings attached. Site deliveries in staged sequence per schedule.
Issued 31 Mar 2026 Deadline 2 months ago (17 Apr 2026) 3 / 3 responded 7 documents
Pricing schedule, round 1
Normalised for AUD, freight, and exclusions. Weighted across four factors. Adjust weights live to stress-test the award recommendation.
Budget $1.5M
Price50
Lead time20
Certification20
Past performance10
| Line item | SP Southcast Precast Australian Certified Top score 93 Price 93 Lead 86 | MF Monolith Fabrication Australian Certified 93 Price 87 Lead 100 | RP Riversand Precast Co Under review 81 Price 100 Lead 71 |
|---|---|---|---|
Precast external panels, Levels 1-14 L-0012 · 2100 m2 Budget $1.5M | $655.00 per m2 Subtotal $1.4M | $698.00 per m2 Subtotal $1.5M | $612.00 per m2 Subtotal $1.3M |
| Freight | $32,000.00 | $38,000.00 | $28,500.00 |
| Currency | AUD | AUD | AUD |
| Lead time | 56 days | 48 days | 68 days |
| Inclusions |
|
|
|
| Exclusions |
|
|
|
| Platform trust | Australian CertifiedKYB verifiedBank verifiedInsurance current | Australian CertifiedKYB verifiedBank verifiedInsurance current | Australian CertifiedKYB verifiedBank verifiedInsurance current |
| Supplier notes | Price assumes release-for-manufacture by end of next month. Standard off-white Class 2 finish. | Premium schedule option available. | Best price based on single-phase delivery. |
| Normalised total, AUD | $1,407,500.00 97% of budget | $1,503,800.00 Over budget by $53.8K | $1,313,700.00 91% of budget |
| Actions |
Recommended award: Southcast Precast
Weighted score 93/100. Normalised total $1.4M. Lead time 56 days. Australian Certified.
Q&A thread
Questions broadcast to all invited suppliers for fairness
Procuralink
3 months ago
RFQ-0021 issued to 3 suppliers. Responses due by deadline.
Kirra Matthews, Southcast PrecastSupplier
3 months ago
Is Class 2 or Class 3 finish required for the north elevation panels? The spec references both in different sections.
Sarah Chen, Meridian DevelopmentsBuyer(broadcast)
3 months ago
Class 2 off-white to all elevations. Spec page 14 confirms, and an updated scope addendum has been attached. Broadcast to all invited suppliers.
Daniel Pham, Monolith FabricationSupplier
2 months ago
Can we propose a single-phase delivery option with pricing for buyer review? Our yard throughput would let us compress the schedule by roughly three weeks.
Sarah Chen, Meridian DevelopmentsBuyer(broadcast)
2 months ago
Yes, submit both a base price per schedule and an alternative single-phase option. Price both separately for like-for-like comparison.
Elena Marchetti, Riversand PrecastSupplier
2 months ago
Our bank account verification is currently in progress with your onboarding team. Will that block award if we are selected?
Sarah Chen, Meridian DevelopmentsBuyer(broadcast)
2 months ago
Bank account verification is required before a PO can be issued, not before award. Please complete with our onboarding team in parallel with final selection.
Procuralink
2 months ago
3 of 3 invited suppliers have submitted a round 1 response. Comparison available on the buyer side.