DiscoveryPrecast concrete
L-0012Precast external panels, Levels 1-14
Architectural precast panels with off-white finish.
Budget $1.5MQuantity 2100 m2 NSW Created 1 month ago
Scoped
Budget $1.5M
2
Quoting
3 responses, round 1
3
Awarded
—
4
Active
—
5
Complete
—
Next action
3 suppliers responded
3 invited, 3 quotes received. Compare normalised pricing and stress-test the weighting.
Deadline 2 days ago · 17 Apr 2026
Quotes received · round 1
3 suppliers, normalised to AUD. Click Compare for the full pricing schedule with weighting.
RP
Riversand Precast Co
Lead 68d · Freight $28.5K
$1.3M
Lowest normalised
SP
Southcast Precast
Lead 56d · Freight $32K
$1.4M
+$93.8K
MF
Monolith Fabrication
Lead 48d · Freight $38K
$1.5M
+$190.1K
Activity
Every event against this line item, most recent first
- Procuralink10 days ago3 of 3 invited suppliers have submitted a round 1 response. Comparison available on the buyer side.
- Monolith Fabrication10 days agoQuote submitted, round 1. Total $1.5M, 48 day lead time.View detail →
- Elena Marchetti, Riversand Precast11 days agoOur bank account verification is currently in progress with your onboarding team. Will that block award if we are selected?
- Sarah Chen, Meridian Developments11 days agoBank account verification is required before a PO can be issued, not before award. Please complete with our onboarding team in parallel w…
- Riversand Precast Co11 days agoQuote submitted, round 1. Total $1.3M, 68 day lead time.View detail →
- Daniel Pham, Monolith Fabrication14 days agoCan we propose a single-phase delivery option with pricing for buyer review? Our yard throughput would let us compress the schedule by ro…
- Sarah Chen, Meridian Developments14 days agoYes, submit both a base price per schedule and an alternative single-phase option. Price both separately for like-for-like comparison.
- Kirra Matthews, Southcast Precast17 days agoIs Class 2 or Class 3 finish required for the north elevation panels? The spec references both in different sections.
- Sarah Chen, Meridian Developments17 days agoClass 2 off-white to all elevations. Spec page 14 confirms, and an updated scope addendum has been attached. Broadcast to all invited sup…
- Procuralink19 days agoRFQ-0021 issued to 3 suppliers. Responses due by deadline.
- Sarah Chen1 month agoLine item created and scoped
Scope
Request for quotation
RFQ-0021 · Round 1
Document trail
Every document against this line item, from RFQ through to warranty
Scope and design
4