Project
Harbour Residences, Pyrmont
Line item
L-0012 · Precast external panels, Levels 1-14
Included in scope
- Design development and coordination with structural consultant.
- Shop detail drawings to construction-category 3.
- Supply of all materials compliant with the technical specification.
- Fabrication, welding, and surface treatment.
- Quality assurance documentation pack for every delivery tranche.
- Delivery to site on nominated milestone dates.
- Defects liability in accordance with the head contract.
Excluded from scope
- Site craneage and offload beyond initial positioning.
- Grouting, bedding, and temporary propping.
- Permits, traffic management, and out-of-hours access.
- Site welding or erection works unless separately priced.
Key dates
| Milestone | Owner | Target |
|---|
| Release for manufacture | Buyer | T + 14 days |
| Shop drawings submitted | Supplier | T + 28 days |
| First delivery to site | Supplier | T + 70 days |
| Final delivery | Supplier | T + 140 days |
Scope is subject to the commercial terms agreed in the purchase order and the technical specification referenced above. Variations shall be priced and approved through Procuralink prior to being actioned.
Issued via Procuralink · audited workflow · Meridian Developments
HR-PRECAST-SCOPEPage 1 of 1