Best and finalRound 2

Glazing, Harbour Residences

Double glazed units with low-e coating for levels 1 to 14.

Issued 23 Mar 2026 Deadline 4 days ago (15 Apr 2026) 2 / 3 responded 4 documents

Pricing schedule, round 2

Normalised for AUD, freight, and exclusions. Weighted across four factors. Adjust weights live to stress-test the award recommendation.

Budget $980K
Price40
Lead time30
Certification20
Past performance10
Line item
CG
Coastline Glazing Systems
Australian Certified Top score
97
Price 94
Lead 100
KF
Kingsway Facade Group
Australian Certified
95
Price 100
Lead 89
Glazing, Levels 1-14
L-0018 · 1850 m2
Budget $980K
$512.00
per m2
Subtotal $947.2K
$478.00
per m2
Subtotal $884.3K
Freight$22,500.00$29,000.00
CurrencyAUDAUD
Lead time
66 days
74 days
Inclusions
  • Design and shop drawings
  • QA pack
  • Low-e coating
  • Commissioning support
  • Design development
  • Shop drawings
  • Warranty extension
Exclusions
  • Site sealants
  • Site sealants
Platform trust
Australian CertifiedKYB verifiedBank verifiedInsurance current
Australian CertifiedKYB verifiedBank verifiedInsurance current
Supplier notesRevised with tightened schedule and small discount for full award.Revised pricing and minor lead time improvement.
Normalised total, AUD$969,700.00
99% of budget
$913,300.00
93% of budget
Actions
Recommended award: Coastline Glazing Systems
Weighted score 97/100. Normalised total $969.7K. Lead time 66 days. Australian Certified.

Q&A thread

Questions broadcast to all invited suppliers for fairness

7 messages
Procuralink
27 days ago
RFQ-0022 issued to 3 suppliers.
Rob Tanaka, Coastline GlazingSupplier
25 days ago
Confirming low-e coating specification; we assume PPG Solarban 60 unless otherwise stated.
Tom Whitfield, Meridian DevelopmentsBuyer(broadcast)
25 days ago
Solarban 60 is acceptable. Please quote Solarban 70XL as an alternative with cost and schedule delta.
Marcus Webb, Kingsway FacadeSupplier
23 days ago
Our Melbourne plant has capacity but freight to Pyrmont adds meaningfully to our landed cost. Any flexibility on staged release to reduce truck loads?
Sarah Chen, Meridian DevelopmentsBuyer(broadcast)
23 days ago
Yes. Please submit a staged release schedule for buyer review alongside single-shipment pricing.
Sarah Chen, Meridian DevelopmentsBuyer(broadcast)
8 days ago
Shortlisted: Coastline and Kingsway. Shortlisted suppliers are invited to a best-and-final round. Revised responses due tomorrow. Declined supplier has been notified.
Rob Tanaka, Coastline GlazingSupplier
6 days ago
Revised response submitted. We have absorbed the specification upgrade at no change to freight. Lead time reduced by 4 days by bringing forward shop drawing release.