DiscoveryGlazing and windows
L-0018Glazing, Levels 1-14
Double-glazed units for residential tower.
Budget $980KQuantity 1850 m2 NSW Created 3 months ago
Scoped
Budget $980K
2
Quoting
2 responses, round 2
3
Awarded
—
4
Active
—
5
Complete
—
Next action
Best-and-final round open
Shortlisted suppliers have revised. 2 responses in. Award the winner.
Deadline 2 months ago
Quotes received · round 2
2 suppliers, normalised to AUD. Click Compare for the full pricing schedule with weighting.
KF
Kingsway Facade Group
Lead 74d · Freight $29K
$913.3K
Lowest normalised
CG
Coastline Glazing Systems
Lead 66d · Freight $22.5K
$969.7K
+$56.4K
Activity
Every event against this line item, most recent first
- Rob Tanaka, Coastline Glazing2 months agoRevised response submitted. We have absorbed the specification upgrade at no change to freight. Lead time reduced by 4 days by bringing f…
- Coastline Glazing Systems2 months agoQuote submitted, round 2. Total $969.7K, 66 day lead time.View detail →
- Kingsway Facade Group2 months agoQuote submitted, round 2. Total $913.3K, 74 day lead time.View detail →
- Sarah Chen, Meridian Developments2 months agoShortlisted: Coastline and Kingsway. Shortlisted suppliers are invited to a best-and-final round. Revised responses due tomorrow. Decline…
- Blackwood Glazing3 months agoQuote submitted, round 1. Total $902.8K, 110 day lead time.View detail →
- Kingsway Facade Group3 months agoQuote submitted, round 1. Total $935.7K, 78 day lead time.View detail →
- Coastline Glazing Systems3 months agoQuote submitted, round 1. Total $993.4K, 70 day lead time.View detail →
- Marcus Webb, Kingsway Facade3 months agoOur Melbourne plant has capacity but freight to Pyrmont adds meaningfully to our landed cost. Any flexibility on staged release to reduce…
- Sarah Chen, Meridian Developments3 months agoYes. Please submit a staged release schedule for buyer review alongside single-shipment pricing.
- Rob Tanaka, Coastline Glazing3 months agoConfirming low-e coating specification; we assume PPG Solarban 60 unless otherwise stated.
- Tom Whitfield, Meridian Developments3 months agoSolarban 60 is acceptable. Please quote Solarban 70XL as an alternative with cost and schedule delta.
- Procuralink3 months agoRFQ-0022 issued to 3 suppliers.
- Sarah Chen3 months agoBest-and-final round opened with shortlisted suppliers
- Sarah Chen3 months agoLine item created and scoped
Scope
Request for quotation
RFQ-0022 · Round 2
Document trail
Every document against this line item, from RFQ through to warranty