L-0031 · Lift package, 12 cars
Chain of custody verifiedUploaded 25 Mar 2026, 11:30 pm1094 KBSHA-256 specf91…a3cecProject: South Yarra Mixed Use
Procuralink
Lift package, 12 cars
South Yarra Mixed Use — Specification package
Reference
SY-LIFT-TECHNICAL-SPEC
Issued
25 Mar 2026
Discipline
Structural

1.Scope of specification

This specification covers the design, fabrication, supply, and delivery of Lift package, 12 cars for the South Yarra Mixed Use. It defines performance requirements, materials, tolerances, quality assurance, and documentation deliverables.

The works comprise a total of 12 cars and shall be completed to the schedule outlined in Section 9.

2.Standards and compliance

  • AS/NZS 4100 — Steel Structures
  • AS/NZS 1554 — Structural steel welding (Part 1, 3, 5 as applicable)
  • AS/NZS 5131 — Structural Steelwork Fabrication and Erection, Construction Category 3
  • AS/NZS ISO 9001 — Quality management
  • National Construction Code (NCC) 2022 Volume One

3.Materials

GradeStandardApplicationYield (MPa)
300PLUSAS/NZS 3679.1Hot-rolled sections300
350L15AS/NZS 3678Plate, CAT-3 welded350
C450L0AS/NZS 1163Hollow sections450
Class 8.8AS 1252High strength bolting660

4.Tolerances

All fabrication and erection tolerances shall conform to AS/NZS 5131 Construction Category 3. Flatness and straightness tolerances: member length divided by 1000, not exceeding 10 mm. Connection plate flatness: ±1.5 mm across any 300 mm gauge length.

5.Surface treatment

All exposed steel shall be shot-blasted to Sa 2.5 (AS 1627.4) immediately prior to priming. Primer: inorganic zinc silicate 75 µm DFT. Intermediate: epoxy mastic 125 µm DFT. Topcoat: polyurethane 75 µm DFT in RAL 7016 anthracite grey unless otherwise nominated.

6.Quality assurance

  • Inspection and test plan (ITP) issued prior to commencement.
  • Weld procedure specifications (WPS) approved to AS/NZS 1554.1.
  • 100% visual inspection, 10% NDT (MPI or UT) of full-penetration welds.
  • Mill certificates retained for all material batches.
  • QA documentation pack issued with every progress delivery.

7.Documentation deliverables

  1. Shop detail drawings — 4 weeks before fabrication.
  2. WPS and welder qualifications — prior to first weld.
  3. Mill certificates and NDT reports — on progressive delivery.
  4. Final QA pack — within 14 days of practical completion.

8.Programme

Works shall commence no later than 14 days after release for manufacture. Progressive deliveries shall align with the construction program.