Helix-commissioning-plan-MT.pdfqa
L-0055 · HVAC primary plant
Chain of custody verifiedUploaded 5 Dec 2025, 11:30 pm527 KBSHA-256 ningf91…a3cngSupplier: Helix HVAC SystemsProject: Meridian Tower, North Sydney
Procuralink
Quality assurance report
HVAC primary plant
Reference
Helix-commissioning-plan-MT
ITP reference
ITP-0031-R2
Test date
5 Dec 2025
Supplier
Helix HVAC Systems
PO
PO-0098
Project
Meridian Tower, North Sydney
Tranche
Progress delivery 1

Inspection outcomes

Hold pointStandardAcceptanceResultOutcome
Mill certificatesAS/NZS 3679.1All batches traceable84 batches, 100% traceablePass
Welder qualificationAS/NZS 1554.1Current WPQ on file12 welders, all currentPass
Visual weld inspectionAS/NZS 1554.1 cl 6.2100% of welds100%Pass
Non-destructive testingAS/NZS 1554.1 cl 6.310% MPI of full-pen welds12% sampled, 0 defectsPass
Paint DFTAS 3894275 µm ± 25Mean 281 µm, SD 9Pass
Dimensional surveyAS/NZS 5131 CC3±3 mm across lengthMax deviation 2.4 mmPass
Bolting torqueAS 4100Spec table 15.2.5Torqued and witnessedPass
Packaging and markingsProject QA plan s.7Piece-marked, match delivery manifestAudited at dispatchPass

Non-conformances

No non-conformances raised this tranche. Previous NCR-0008 (paint DFT underspec on 2 members) closed with rework on 29 Nov 2025.

Attached evidence

  • Mill test reports (MTRs) — 84 PDF files, batch-indexed
  • Weld map with NDT stamps, Levels 1 to 4
  • DFT log (40 readings per member)
  • Dispatch manifest with piece marks
Helix P.
QA manager, supplier
Helix Park
5 Dec 2025
Tom W.
Verified by buyer
Tom Whitfield
5 Dec 2025
Issued via Procuralink · audited workflow · Helix HVAC Systems
Helix-commissioning-plan-MTPage 1 of 1