L-0047 · Unitised facade, Levels 1-18
Chain of custody verifiedUploaded 26 Sept 2025, 11:30 pm938 KBSHA-256 specf91…a3cecProject: Meridian Tower, North Sydney
Procuralink
Unitised facade, Levels 1-18
Meridian Tower, North Sydney — Specification package
Reference
MT-FACADE-SPEC-AS-NZS-5113
Issued
26 Sept 2025
Discipline
Structural

1.Scope of specification

This specification covers the design, fabrication, supply, and delivery of Unitised facade, Levels 1-18 for the Meridian Tower, North Sydney. It defines performance requirements, materials, tolerances, quality assurance, and documentation deliverables.

The works comprise a total of 3,200 m2 and shall be completed to the schedule outlined in Section 9.

2.Standards and compliance

  • AS/NZS 4100 — Steel Structures
  • AS/NZS 1554 — Structural steel welding (Part 1, 3, 5 as applicable)
  • AS/NZS 5131 — Structural Steelwork Fabrication and Erection, Construction Category 3
  • AS/NZS ISO 9001 — Quality management
  • National Construction Code (NCC) 2022 Volume One

3.Materials

GradeStandardApplicationYield (MPa)
300PLUSAS/NZS 3679.1Hot-rolled sections300
350L15AS/NZS 3678Plate, CAT-3 welded350
C450L0AS/NZS 1163Hollow sections450
Class 8.8AS 1252High strength bolting660

4.Tolerances

All fabrication and erection tolerances shall conform to AS/NZS 5131 Construction Category 3. Flatness and straightness tolerances: member length divided by 1000, not exceeding 10 mm. Connection plate flatness: ±1.5 mm across any 300 mm gauge length.

5.Surface treatment

All exposed steel shall be shot-blasted to Sa 2.5 (AS 1627.4) immediately prior to priming. Primer: inorganic zinc silicate 75 µm DFT. Intermediate: epoxy mastic 125 µm DFT. Topcoat: polyurethane 75 µm DFT in RAL 7016 anthracite grey unless otherwise nominated.

6.Quality assurance

  • Inspection and test plan (ITP) issued prior to commencement.
  • Weld procedure specifications (WPS) approved to AS/NZS 1554.1.
  • 100% visual inspection, 10% NDT (MPI or UT) of full-penetration welds.
  • Mill certificates retained for all material batches.
  • QA documentation pack issued with every progress delivery.

7.Documentation deliverables

  1. Shop detail drawings — 4 weeks before fabrication.
  2. WPS and welder qualifications — prior to first weld.
  3. Mill certificates and NDT reports — on progressive delivery.
  4. Final QA pack — within 14 days of practical completion.

8.Programme

Works shall commence no later than 14 days after release for manufacture. Progressive deliveries shall align with the construction program.

Issued via Procuralink · audited workflow · Meridian Developments
MT-FACADE-SPEC-AS-NZS-5113Page 1 of 1